Pembrokeshire County Council Performance |
Actual 2015/16 |
Actual 2016/17 |
Levels of preparing for reuse and recycling/composting (or Anaerobic Digestion) for municipal waste. |
64.9% |
65.4% |
BMW (Biodegradable Municipal Waste) Landfilled |
6,523 tonnes |
5,046 tonnes |
Whilst this is a commendable achievement we can see that there is still much to do if we are to continue these trends and meet the targets of 2019/20 and beyond.
A financial penalty of £200/tonne is incurred if the Council fails its recycling targets. This would have severe implications for the Council.
To fail the recycling target by just 1% would equate to approximately 700 tonnes.
The financial penalty incurred could be:
700 tonnes x £200/tonne = £140,000